Overdue Update

November 16, 2009 by dylee13

Hi everyone! Obviously, we are not doing well at keeping up with this blog, and for those of you who are friends with us on facebook, you know that many things have been happening over the last couple months.

First big thing – we passed our inspections! Whoo-hoo! That was a huge hurdle for us. It basically means that the city approves of our house and has deemed it safe and up to code. It took 3 tries and lots of back-and-forthing with the building department before we were finally able to satisfy the inspectors.

The most exciting part of passing inspections meant that we could start “closing up” the walls, i.e. putting in insulation and hanging sheetrock! So after a couple weekends of finishing up last minute things, we hired some day laborers and they installed our insulation.

IMG_4410

IMG_4617

Who doesn’t love insulation? Keeps the house cool when it’s warm outside and keeps it warm when it’s cold…very good stuff. Unfortunately, it is also very itchy. Itchy, itchy, itchy.

After the house was insulated, we had the sheetrock guys deliver their supplies…and then they started hanging! How cool is this?

IMG_1536

IMG_1544

IMG_1554

It’s starting to look like a house again! I can’t even begin to tell you how excited I’ve been about sheetrock…excitement on so many levels? Can I list a few reasons?

* We’re starting to see the finish line (at least until we can move in)

* It covers up the itchy insulation

* Work is happening at the house when Ryan and I are NOT there

* I think this will be the end of all that crazy martian dust insulation that keeps showing up

…and many many more.

Now that the sheetrock is hung, we apparently need another inspection, and  then the sheetrock guys will start mudding and sanding. The excitement keeps growing!

slowly coming along…

October 6, 2009 by dylee13

okay. so in the last…what has it been? two months? since our last update, we’ve had a couple of fairly significant things happen.

1) We got our building permit signed off! Whoo hoo! It took two visits from the building inspector, some foam insulation installation (and then removal), fire-retardant caulking stuff, and lots of praying, but we are just about good to start installing insulation and closing things up.

2) However, we did not pass our plumbing inspection. It has something to do with the way our pipes are vented – I never even knew pipes had to be vented, but I guess it makes sense now that I think about it. So we are going to have our plumber guys re-vent things and then we will be even closer to closing things up.

In the meantime, we are doing all sorts of miscellaneous things to provide further support to our house – installing things called “straps,” putting in additional hold-downs (i.e., making sure the house is really really stuck to the foundation), and more waterproofing.

That’s right. We’re still waterproofing our downstairs room. Ryan found another waterproofing system – an acrylic surface-applied thingy – and we’ve been applying that to the concrete. Hopefully, all these things we’ve done will work and the master bedroom will stay dry this winter.

We started putting in some insulation in one of the rooms in the house. Here are some pictures of that:

before the insulation

IMG_4273

insulation
IMG_4279

plywood over the insulation

IMG_4280

We’re hoping that we’ll be able to put insulation in the rest of the house in the next coming weeks…and after that comes sheetrock!

The Most Significant Thing We’ve Done

August 31, 2009 by dylee13

We bought our house almost 50 weeks ago and started demolition about 11 months ago. New concrete has been poured, walls have been built, a new subfloor installed, and a hole was cut for the stairs. But this past weekend, we made the most significant change to the house so far. If you recall, our house has a pitched roof – that is, it’s not flat. It comes to a point at the top. In order to maintain this shape there are horizontal pieces of wood running from one side of the house to the other. These pieces of wood are, essentially, pulling the exterior walls of the house together and preventing the whole house from going splat.

new roof framing

original wooden beams

The goal this weekend was to replace 4 of the wooden beams with steel rods, with the eventual plan of cutting down the rest of wood and having those 4 rods do the work of 12 or so wooden beams. Crazy stuff, if you ask me.  It was a looooong weekend, and we will be forever in debt to the friends who helped us.  

These are the steel pieces. There are 8 steel rods – 2 for each wooden beam. They meet in the middle and are fastened together by a turnbuckle. Ryan had to thread all the steel rods by hand. On the left side of the picture is one of the steel saddles. This is what anchors the steel rod to the house. Confused? So was I. 

rods and saddles

rods and saddles

 The first step was installing the saddles. Easier said than done. In order to install each saddle, we first had to cut off the 25 foot long redwood beam, install a piece of blocking (sorta like a piece of filler wood), chip out a section of the roof framing so the saddle would be flush, pound the saddle in, drill holes for the bolts, and bolt them in. Sound like a lot of work? There were 8 of the them. 

Ryan, cutting down the existing beam

Ryan, cutting down the existing beam

beam is down, and blocking is in

beam is down, and blocking is in

John, chipping away the extra wood

John, chipping away the extra wood

 

saddle is in!

saddle is in!

 After each set of saddles were installed, we measured the distance between them to determine exactly how long the steel rods needed to be. Then someone had to cut the steel rod to size, which was like watching a fireworks show. 

IMG_3933

measuring

 Once the rods were the proper length, we could finally install them…this part took at least 3 guys: one on each end and one in the middle.

IMG_3943

Screwing the rod to the saddle

The last step was to adjust the middle. Ryan devised a clever way of being able to tighten both rods at the same time using the turnbuckle. I don’t know that I have the words to adequately describe how it works, so I’ll try to get Ryan to describe it later on. I thought it was brilliant.

IMG_3952

Tightening the turnbuckle

One rod finished!

One rod finished!

So with six people, we were able to get 3 of the 4 rods finished in one loooong day.

IMG_3959

 

Denise vs. The Waterproofing

June 16, 2009 by dylee13

If you recall, during the rainy season we had some flooding problems with one of the rooms on the ground floor (what will eventually be the master bedroom). Obviously, this was not part of the original design. So over the past few months, Ryan has been investigating various waterproofing products. After consulting with a waterproofing specialist (who knew such a thing existed?), Ryan discovered a product known as Xypex. 

xypex

 

 

 

 

According to their website, Xypex has “set an international standard for concrete waterproofing. Xypex prevents the penetration of water and other liquids from any direction by causing a catalytic reaction that produces a non-soluble crystalline formation within the pores and capillary tracts of concrete and cement-based materials.” I like the sound of that. Apparently, this is the stuff that gets used to help prevent water leaking into things such as subway stations, tunnels, power stations, and manholes. Ryan figured if it could keep water out of those massive structures, then it would probably due the trick in our little bedroom. 

As this is a somewhat contained, smaller scale project, Ryan delegated nearly all the waterproofing tasks to me. So first came the preparation: stripping the paint off the concrete, chemical etching, power washing, and patching. And then we had to special order the Xypex from someplace in Redding. I was sent to pick up the 60-pound bucket all by myself. It was quite a site to see me trying to lug it from the car into the house.

Finally, after weeks of various obstacles, came the day that I would apply the Xypex. I started the day off with another trip to Home Depot to pick up last minute stuff, including a new Shop Vac. I bought the little bitty baby one because I like things that are a size I can manage. I figured it’ll be easier to store in the future, too.

Then I had do final prep work on the concrete – one more vacuum with the shop vac to get rid of the dust and debris and then I had to spray down and saturate the concrete with water. Last step prior to applying the stuff: mixing it. The Xypex comes in a powder form and gets mixed with water and applied, either with a special sprayer-thingy or a paint brush. As we are not so fancy and do not have a special sprayer-thingy, I went with paint brush.

When I started all this, I figured it wouldn’t be much worse than any other painting project. Slap it on and you’re good to go. But nooo…Xypex is very particular. It requires a wet surface for application, and you have to mix it in small quantities to ensure that the catalytic reaction occurs in the concrete and not in the bucket in which it’s mixed. So this meant I had to mix at least 4 batches of the stuff, and was constantly running for the hose to keep the surface wet. It was slow work applying it, too. Unlike paint, this was more goopy and took some effort to spread around. I spent nearly 4 hours hunched over spreading this stuff around. I got three blisters on my hands and my hands were so tired I could barely write afterwards.  That stuff had me totally beat. Denise – 0 Waterproofing – 1. 

 

bedroom waterproofed (hopefully)

bedroom waterproofed (hopefully)

 

 

 

 

 

 

 

 

 

The worst part about this is that this is pretty much our only shot with this stuff. So if I screwed up at all in the application, it will all be for naught and our bedroom will be forever leaky. So cross your fingers and pray with me that I did it right!

Stupid Garage Door

May 31, 2009 by ryanjang

So it wasn’t such a great time at the house this past weekend.  A couple of things:

FIRST off, I had scheduled the rough framing inspection for Friday afternoon.  So Thursday evening I was at the apartment, trying to get things together.  You need to things to show the inspector:  The job card (showing all the inspection sign-offs, inspectors notes, and dates) and the permit drawings (approved with stamps by the building department).  It turns out that I couldn’t find the drawings, but I easily found the job card.  Denise and I tore the apartment apart, to no avail.  I have no idea where a huge folder of paperwork went, and I just had it a week ago.  I checked at the house, at work, and at home, and the drawings were nowhere to be found.  So I looked pretty dumb, explaining to the inspector that the drawings were lost.  Even worse, he couldn’t sign off on them without seeing the drawings.

 

The SECOND crappy thing was that he wants me to go submit a revision to the building department.  We reinforced the existing roof from the inside, adding new pieces of wood to basically make things stronger.  This decision came after construction had started, so the work was not in the original permit.  The inspector said it wasn’t a big deal, but wanted me to go back to the building department (the evil place with long lines and mean people) and talk to one of the engineers and make sure the work was ok.  Good thing I planned all this out with my awesome structural engineer friend Christian (www.rough-tumble.com) before doing the work.  Still, this means more drawings, delay, and time.  Here’s a picture of our stronger roof, by the way:

 

new roof framing

new roof framing

 

 

 

 

 

 

 

 

 

 

And THIRD, I was all set for a productive afternoon at the house today.  I get started with some work in the garage, and accidentally hit a garage door cable.  You see, our garage door is kinda old.  It’s not all fancy with a motor and remote control and buttons that make it open or close.  You’ve gotta put the key in, unlock it, and lift the damn thing.  There are two cables on each side, attached to a spring, that supposedly help you open and close it easier.  Those cables are actually really important.  So I accidentally hit one of the cables loose, leaving big mess of wire.  I thought that I’d fix it all later, but then found that the dumb door gets stuck without them.  So instead of a productive afternoon, I ended up fixing a garage door that wasn’t very good to begin with.  By the time I was done, it was time for dinner.  Here’s the dumb door that ought to be replaced anyways:

 

Garage Door

Garage Door

 

 

 

 

 

 

 

 

 

 

LAST, and unrelated to the house, I lost my car on Sutter street this morning, and walked around the block twice trying to find it.

All in all, hopefully next weekend will be better.

Mechanical, Electrical & Plumbing Pictures

May 7, 2009 by ryanjang

Here are some more detailed pictures of the MEP work, now finished at the house.  Rough inspections (by the city building department) are tomorrow.  Wish me luck!

Here’s the main duct, covered now in insulation.  Not shown and to the right, the duct starts at the furnace, in the garage.  Ground floor registers are in the ceiling.  Upstairs, the air will come out of the cabinet ‘kick’ or the floor.  The duct will be enclosed in the same cabinet material.

Here’s the electrical sub-panel, with all the circuit breakers.  Power comes from outside PG&E lines overhead, to the main panel with the meter, and then to this sub-panel.  From here, wires to to all the lights and power in ever room.  Different color wires carry different amounts of power.  Orange, for example is 30 amps, going to the electric clothes dryer & oven.

Let there be light!  We tested the lights, to make sure everything works.  This picture is of the recessed cans downstairs.  They’re halogen, uninteresting, and pretty much as cheap as you can get.  At least they line up.

This plumbing picture is taken from the garage.  All the waste lines come to a point before going into the ground and into the main at the street.  All these pipes come from the kitchen and bathroom upstairs.
Plumbing waste lines not only go into the ground, but need to be ‘vented’ to the roof.  Vents provide relief of sewer gases and prevent these gases from entering the building.  With exceptions, every plumbing fixture must have a vent.  In our second floor, only one wall extends to the roof.  All the other walls are partial height and stop at 8′ above the ground.  So to hide all the pipes, they needed to come to this one full height wall, and vented to the roof.  Also in this wall are bathroom exhaust fan vents (in silver) and a flue from the furnace (black plastic).
Lastly, here’s the kitchen sink plumbing.  Since it’s on an island, there’s no place for a regular vent, discussed above.  So the piping has to be configured in what’s called a ‘loop vent’.  It loops around and connects with another pipe, eventually going to the roof.  In the picture, it’s the larger copper pipe, forming an upside down ‘V’.  The 4 smaller copper pipes are the water supply, hot and cold, for both the dishwasher and kitchen sink.  A required ‘clean-out’ is below and behind the blue hose.

Progress!

May 4, 2009 by ryanjang

Hi Everyone,


Again, we haven’t been so great with updating.  This time, we have lots to update.  Also, a side note, I accidentally deleted 3 comments recently.  Sorry about that.  Feel free to repost.

So now, not only do we have floors, but we have walls, pipes, ducts, lights, switches and wires!  Rough plumbing, electrical, and mechanical inspections are scheduled this coming Tuesday.  So enough with words, here are some pictures:

Upstairs framing.  You can see the entrance to the two bedrooms in the middle.  The 8′ high wall is going to contain all the kitchen cabinets.  The bathroom is behind and in he middle.  Only one wall goes up to the high ceiling.  It contains all plumbing vents and is also a structural wall.

















Here’s a close-up of the back of that tall wall.  All the plumbing vents from the entire house come into this one wall, and up to the roof.  The bathroom exhaust fans & furnace flue also comes through this wall.
















Here’s the roof.  The lower pieces of wood spanning across the house will  be removed.  They’ll be replaced with 4 steel rods.  You can see the framing for the skylights to the left.
















More of the upstairs.  The dining room is behind.  The lower wall has the kitchen sink plumbing.  The island will go in front.

















View from the back of the house.  You can see the hole where the stairs are going to the right.
















Close-up of the stair hole.  It starts at the far point from the camera, and turns an ‘L’ as you descend.















This photo is from the entertainment room downstairs.  It’s looking toward the stair hole and the master bedroom beyond.  To the right is the garage.  The yellow thing in the ceiling is insulation, covering a duct.  One main heating duct runs from the front of the house to the back, with registers that admit heat, to each of the upstairs and downstairs rooms.  The rectangles with circles in them are the recessed lights.

Good times…they are a-coming!

April 7, 2009 by dylee13
We had the best weekend last week! We got floors AND walls! It was so exciting. We hadn’t anticipated so much getting done. But just to clarify, when I say walls, I mean the framing that holds up the sheetrock. There are still many many steps before we even get close to sheetrock. So this is what we’re working with now…
This is the only wall in the house that will go completely from floor to ceiling (at least on the main level of the house). It is the wall between the upstairs bathroom and one of the bedrooms:

And this is Ryan, constructing the half wall that will act as a guard rail for the stairs and where the kitchen counters will be:

These rooms are the upstairs bathroom and bedroom. The smallish square room toward the right of the picture is where the bathroom will be (it is in the running for world’s smallest bathroom). The room toward the back of the house is the bedroom. To the left of the bedroom is where the kitchen will be.

And here is more or less the completed walls. As you can see, with exception of one of the bathroom walls, none of them are full height (meaning they don’t go up to the ceiling). Yes, that’s right. All the rooms will be open on top. If you were a 12-foot giant, you could walk around and look down into each room (except the bathroom, which will have a lid on it to provide…ahem…acoustical privacy). 

The room toward the right of the bathroom could be like another bedroom (it will have a closet and a window, which technically makes a bedroom). More likely, for us, it will serve as an office. It is not completely enclosed by walls because, in the very very far future, Ryan wants the center wall to made of GLASS.  

So those are just about all the walls that will be in the house. The next steps include putting in blocking (horizontal pieces of wood that go in between the vertical pieces in the wall), which provide some kind of stability to the wall. And then we need to do plumbing and electrical work. And there are a bunch of odds and ends that need to be done…but this was a huge step since it was the first time that we really put in something new in the house. Go us!

Playing catch-up

March 31, 2009 by dylee13

Ryan and I are very aware that we are not doing a good job updating this blog. Since our last post, a lot has happened at the house. I am going to attempt to catch y’all up with what’s been going on: 


The first major thing that happened was that we had a swimming pool installed. For those of you in the bay area, you might remember that for a few weeks in February we were getting a LOT of rain. During one of those weeks, Ryan sent me over to the house on a random errand and I found a swimming pool where we had intended to put our master bedroom. We were so freaked out by the incident that we didn’t have the presence of mind to take pictures. Here’s a picture of the draining swimming pool:

When I first found the pool, the entire room was covered in about an inch and a half of water. We think that ground water was leaking in through the edges of the room. Now that it has stopped raining, we are working on waterproofing the problem areas so that this doesn’t happen every time it rains.


The next big thing that happened is that we tore up the subfloor on the main living floor in order to reinforce some of the old joists and level the floor. This has been quite an adventure. So this is what we’ve been dealing with:

You can see we’ve put sheets of plywood and other pieces of wood down on top of the joists so that we can walk around, but I’ve got to say, I’ve never really appreciated the benefits of having a floor. Luckily, we are now in the process of putting the new subfloor in. Can’t wait to have floors again! 

Finally, the last big thing that’s happened is that Ryan constructed our first wall! It is the wall that separates the garage area from the living area on the ground floor. Unfortunately, I can’t find the pictures of it, so that will have to wait for another post. But it is very exciting to me that we are finally BUILDING walls instead of tearing them down. 

Floors and walls. Good times are ahead.

Design Images

January 21, 2009 by ryanjang
I thought I’d post some images of what the house is intended to be, when it’s all said and done.  I’ve been using Autocad to draft up plans, sections and elevations of the design.  Autocad is practically the industry standard for architects and some engineers to draft drawings of various sorts in the computer.  It’s sort of like drafting things by hand except faster.  The images below, however, were done in a 3D modeling program called Sketchup.  It is a very simple program, also free from google.  It’s super-easy to use and a convenient way to visualize spaces and objects in three dimensions.  Therefore, its a good tool to understand the spaces prior to building them to make sure everything works out.  This particular program isn’t the best tool for photo-realistic renderings, but it works for simple exercises like this.

Below are two images, one from a birds-eye view and another at eye level.  The street and front entry are at the second floor to the left.  The backyard is to the right.  You enter the house from an exterior staircase leading to the second floor.

As you enter, you find yourself in the living room.  To your right is the third bedroom which will most likely be used as an office.  The staircase and kitchen are integrated, and are located behind the living room.  The ‘island’ kitchen counter, shown in dark brown, will contain the sink and will serve as the guardrail so you don’t fall to the floor below.  To the top of the drawing is the bathroom flanked on each side by bedrooms.

A tall wall of cabinetry, shown in tan,  separates bedroom 2 from the kitchen. Starting from the top right, this cabinetry forms the closet for bedroom 3, a coat closet facing the living room, tall kitchen items (refrigerator, pantry, oven, appliance garage), and a counter for the stove.  In addition to being a room divider, this cabinetry will also hide ductwork at it’s base, supplying the heat to all rooms of the house.  It also contains the energy efficient up-lights at the top, which will shine onto the high ceiling above.  The lights will be hidden from one’s view.  Since the fluorescent lights will reflect from the ceiling, the harshness typically associated with fluorescents will be reduced.  Therefore the tan ‘L’ functions as a divider of space, storage for a variety of functions, and a conduit for electrical and heating utilities.  It’s called ‘poche’, ‘diagram’, or ‘parti’ in archi-speak.

As the cabinet wall will stop well short of the ceiling, the only wall in the middle of the house that extends from floor to ceiling is between ‘bath 1′ and ‘bdrm 2′.  This wall provides structural, lateral support and holds the plumbing utilities.  Every other wall stops at an 8′ high datum.  This will provide greater natural light to all spaces and will allow you to perceive the high cathedral ceiling from all rooms in the house.  Since the home is small and square footage is not very generous, a high ceiling and open plan will help to make the house feel larger and more comfortable.

The kitchen counter, shown in dark brown, stops and then starts again in the dining room.  The dining room is located in the existing sunroom addition.  This will be right next to the deck.  I hope to eventually put a large sliding door between the deck and dining room, allowing the eating area to open to the outside on a warm day.  The ceiling over the dining room is lower than the rest of the house.  I’m thinking to paint this entire volume a fun, bright color, giving a counterpoint to the white walls and ceiling.

The staircase leads you down toward a bookshelf and then under the kitchen counter.  Usually, there are cabinets under counters, but to allow headroom without sacrificing valuable space, we’re going to omit the cabinets, allowing headroom as you descend the stairs.  The stair landing is about 2′-6″ above the ground floor level, the ideal desk height.  This landing forms a ‘plinth’ and will extend to the right, beyond the stair, forming a desk at the office area.

To the right of the office will be the family room.  Because of the exterior stair, this area has little natural light.  The open stair and skylights at the roof above will help bring light to the dark ground floor level, but this area will be ideal for an entertainment center and tv.

To the left of the stairway, under the dining room, will be the master bedroom.  Eventually, similar to upstairs, I’d like to add a large sliding door.  On nice days, the master bedroom will have direct access to the backyard and garden. (as if we have any idea how to garden)

Not shown is the garage and master bathroom on the ground floor.  The garage basically stays in the same place, and will house the water heater, a laundry area, furnace, and electrical panel as well as one car.  Behind the garage, and next to the office, will be the master bathroom.

All in all, we’ll have about 1500 habitable square feet, 3 bedrooms, and 2 bathrooms.  We’re trying to make the most out of a small space.  Hopefully, every square inch will be utilized efficiently and simply.  In addition, the design will try to take advantage of an open floor-plan, high ceilings, and visual connection between the two floors.  This should give a generous and open feeling to a space that could easily feel cramped.  With a tight budget, locating plumbing and heating systems in a straightforward and simple manner will help to keep costs down.

Here are those images:





















Those are my thoughts so far.  Any feedback or suggestions would be appreciated, preferably before I start to build walls!